Cannot Update Actuals in project properties project list

Document ID : KB000004490
Last Modified Date : 14/02/2018
Show Technical Document Details
Issue:

Not able to see actuals in project properties and project list, you fill actuals and it appears on team tab and gantt view, but in a project level is not possible to update.

Environment:
All CA PPM Versions.
Cause:

A job is required to post actual in a  project level.

Resolution:

You should run the following job:

   Investment allocation

With that job you update actuals in a project level and project list as well.