Can we make Cost Types WIP Adjustments?

Document ID : KB000028501
Last Modified Date : 14/02/2018
Show Technical Document Details

If an actual transaction was posted into WIP with an incorrect Cost Type (Operating or Capital), it can be corrected by using the following steps:

  1. Login to Clarity as a user that has the access rights that allows you to change the Cost Type on a Project Task.
  2. Locate the task associated with the actual transaction and change the Cost Type
  3. Go to 'Create WIP Adjustment' list page ; locating the specific transaction
  4. Open the transaction and click 'Save' button -- NO need to make any changes to the transaction
  5. The transaction will show up on the 'Approve WIP Adjustment' listing
  6. Approve the Adjustment
  7. Now the transaction will have the correct Cost Type associated.