Issue:

When adding work to a timesheet, the following error is displays:
TMA-1003: Resource assignment is either invalid or there is already an existing time entry for the assignment: Resource ID

Cause:
This is due to a project team or task configuration issue.
Resolution:
Check if one of more of the following is required:
-Is the user a team member of the project and assigned to the task?
-Change the project task status to 'Started'