CA PPM New UX Timesheet shows "Other Work" as a 5XXXXXX and does not reflect the name in Classic PPM

Document ID : KB000106379
Last Modified Date : 19/07/2018
Show Technical Document Details
Issue:
When I add "Other Work" to my Timesheet via the New UX the "Work Name/ID" shows as a 5XXXXXX number and not the "Other Work" name in Classic PPM.

Steps To Reproduce:
1. Create a new Timesheet in the New UX
2. Choose Type: Other Work
3. Click the Add and Close button 
Expected Results: In the "Other Work" section of the timesheet the name should appear as it appears in Classic PPM.
Actual Results: The "Other Work" name appears as a 5XXXXXX number.
Environment:
CA PPM 15.3 and higher
Cause:
This is due to the task name in the XOG Object: inv_others_write.xml.
Resolution:
I renamed the "Other Work" task name in XOG Object: inv_others_write.xml to reflect the "Other Work" name ID in Classic PPM.