Issue:
For some resource the 'Add assigned task' option is missing in the PPM/Clarity New User Experience (UX) when creating a new timesheet.
Resolution:
Check to make sure the resource has one or more assigned task(s) that meet the below criteria:
  • The assignment start/finish dates fall within the system timesheet population window set in PPM in Administration->Timesheet Options. (Whether ETC on the task is 0 or not). 
  • Or any tasks assigned with non-zero remaining ETC in time periods that occur after the assignment finish date
Note: 
  • Furthermore, the ‘’Add assigned task’’ option cannot be removed by default if any tasks meet the criteria to show up on the timesheet in the New User Interface/Experience.