Issue:
Financial transactions created either manually or through XOG and posted to WIP but the transactions do not show on the tasks.

 
Cause:
Because of an old defect, there are times when the assignment cannot be created when running the Import Financial Actuals job.

You will see error in bg-ca logs similar to 

ERROR 2015-01-20 10:30:01,598 [Dispatch pool-5-thread-2 : bg@us2app042.ondemand.ca.com (tenant=clarity)] xql2.xbl (clarity:admin:9961048__5FBB1DA8-55F5-4F4E-AF3A-C4FD74EBDABB:Import Financial Actuals) ****IMPORT WIP ACTUALS: Failed to create assignment for WIP record ID = 5008010 
Resolution:
First make sure you run job Import Financial Actuals.

If the job runs and you still do not see the actuals check to see if the resource is actually on the team and assigned to the task in question. 

If not, assign the resource to the team and the task and then run

Import Financial Actuals job again.

The record should then process and you will see it on the task/assignment.